Construction time: 2011 August Location Construction site: Shanghai Yangpu District No. 1061 Xuchang road block
Project brief introduction:This works for the old plant substation reconstruction project. The substation ground and three floors, building area of about 264m2, the existing 2 1000KVA / 10 / 0.4KV oil-immersed transformer, a 10KV power supply. After the transformation, substation composed of two 10KV power supply, one with a preparation, can satisfy two class power supply requirements. Transformation of high, low-voltage distribution system, equipment updates, local adjustment of plane separation.